Un seul soumissionnaire en lice pour construire les centrales Koudiet Edraouch and Terga
APS Algiers - The consortium formed by the French company Alstom and the Egyptian group Orascom was the only bidder that submitted a bid for the construction of commercial power plants and Koudiet Edraouch Terga d a total capacity of 1200 MW each at the end of a public opening of financial bids for these projects. Regarding the central Koudiet Edraouch (El Tarf), KW installed is estimated at 1,757 dollars, while the average cost per KW / h was estimated at 4.83 dinars. KW installed power plant Terga (Ain Temouchent) is estimated, meanwhile, in 1625 dollars, while the average cost per KWh is 4.48 dinars.